Federal regulators have approved plans to load radioactive fuel into a second new nuclear reactor in Georgia. The Nuclear Regulatory Commission said Friday that Georgia Power Co. and its co-owners can begin loading fuel into unit 4 at Plant Vogtle, southeast of Augusta.
Years of cost overruns at the nuclear expansion at Plant Vogtle have made the project a poor deal for Georgia Power customers, an expert with the PubliC Service Commission said Thursday.
On Friday, Georgia Power announced that a new nuclear reactor at Plant Vogtle is on its way to becoming fully operational in the coming months, news that comes several days before the utility faces another showdown over the project’s ballooning costs brought on by years of delays.
On the Friday July 21st edition of Georgia Today: A former Dougherty county administrator is suing the county over his termination; A new stamp honoring the life and legacy of Congressman John Lewis is available today; And the first sea turtles to emerge from this year's nesting season on the Georgia coast have hatched.
Commercial operation of a new reactor at a Georgia nuclear power plant has been delayed for at least another month. Georgia Power Co. said Friday that Unit 3 at Plant Vogtle has a problem in the hydrogen system that cools its electrical generator.
Vogtle’s electricity won’t just be used on Georgia’s homes and businesses. Power from the nuclear plant will also be sold to Alabama properties and to Florida customers of the Jacksonville Electric Authority.
A new reactor at a nuclear power plant in Georgia has reached its full power output for the first time. Georgia Power Co. announced Monday that Unit 3 at Plant Vogtle has reached its full output of 1,100 megawatts of electricity.
The first new U.S. nuclear reactor built from scratch in decades has begun generating electricity. The lead owner of Georgia Power Co. says the reactors are a success. But the project is $17 billion over budget and seven years late.
Electricity bills for Georgia Power Co. customers will be going up 12% beginning in June. Georgia's elected public service commissioners on Tuesday unanimously approved the boost to make up for the higher cost of fuel.
Georgia Power executives predict the nation’s first nuclear plant expansion in over 30 years is just several weeks away from Plant Vogtle’s reactor generating electricity that will meet its customer’s energy demands for decades to come.
A nuclear power plant in Georgia has begun splitting atoms in one of its two new reactors. Georgia Power Co. announced the key step toward reaching commercial operation on Monday. The utility and other owners are building the first two nuclear reactors constructed from scratch in the United States in decades.
Georgia Power Co. bills could go up another 17% in June to cover the higher costs of natural gas and coal. The unit of Atlanta-based Southern Co. told regulators Tuesday that it needs to collect billions more to pay for the fuel it burns to generate electricity for its 2.7 million customers.
Georgia Power Co. has again delayed the projected startup for two new units at its Vogtle nuclear power plant near Augusta, saying its share of the costs will rise by an additional $200 million.
Startup of a nuclear power plant in Georgia will be delayed after its operator found a vibrating pipe in its cooling system. Georgia Power Co., the lead owner of Plant Vogtle near Waynesboro, announced the delay Wednesday.